Projects

Industrial

R22 System Replacement for Iconic Biscuit Manufacturer

We replaced the ageing synthetic refrigerant chillers utilised across the site. These serve factory and administration process cooling and air conditioning loads.

Client Objectives:

  • Remove ageing plant, R22 and other synthetic refrigerants from the site
  • Increase overall cooling capacity to meet current and future growth
  • Utilise natural refrigerants to meet all cooling loads
  • Achieve high levels of system efficiency without impacting operational reliability
  • Ensure the safety of site and maintenance staff at all times
  • Deliver 30 year plant life expectancy

Key Points

A new central plant room constructed to meet the full site's cooling requirements
The refrigeration plant and components designed to FM Global requirements
8,000kW of refrigeration across four separate systems connected to a common chilled water and common glycol reticulation system
Four vessels, with well over 2km of pipework ranging from 20NB to 450NB
Ammonia refrigerant limited to the plant area with chilled glycol / water reticulated to all cooling loads throughout the facility
All internal areas metal sheathed with 304 grade stainless steel and foam injected
All external areas metal sheathed with galvanize and foam injected

Related Projects.

Industrial

MSF Sugar

Green Energy Power Plant Construction company, Thyssenkrupp Industrial Solutions contracted Advanced Insulation and Fabrications for this project. The 24MW bagasse-fired...
Industrial

Queensland Tissue Products

The Project Insulating and cladding of large PM1 hood ducts and steam piping insulation for recycled soft tissue. The Challenge...